Task plan has not been released (tcode SCMA) CharM

Former Member
0 Kudos

Hello!

I have created a task plan and would like to execute some tasks in Tcode SCMA.

Even when I push some task I get the warning:

<b>"Task plan has not been released".</b>

When I try to activate task list I get the error:

<b>"Phase change from 'Created' to 'Development without Release' is not possible'"</b>

How can these problems be solved ans the task plan be activated?

Thank you very much!

regards

Thom

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi Thom,

your issue is because you haven't created a Business Partner for your userId.

Use transaction BP and create a business partner view and the Employee view as well.

Hope this helps.

Salpi

P.S. Please reward for any helpful questions or solutions.

Former Member
0 Kudos

have you seen this thread?

Former Member
0 Kudos

Hi,

as long as your logical components is not in line with your STMS, SolMan will not be able to generate the correspondign Task List and as a result you always get this message.

kr,

Oliver

Former Member
0 Kudos

Hi Tom,

I'm getting the same problem, how did you resolve this please.

Thanks

Former Member
0 Kudos

Hi!

The error could be:

- you have wrong assignement of correction/urgent correction to IBase (you need IBase of productive system)

- you can face with configuration error (wrong system roles in solar_project_admin, wrong TMS configuration)

Try this please

regards

Thom

Former Member
0 Kudos

Thanks Thom, actually I've fixed my problem now which was BP related.