on 11-02-2007 6:11 PM
Hello!
I have following questions regarding CharM functionality:
Tcode /TMWFLOW/PROJ --> Scheduling --> push "Advance"
or tcode SCMA
I am getting the error "There is no task list for this project"
Question: How can task list be created?
Tcode /TMWFLOW/PROJ --> Project Structure
CTS project --> status in task list LOCKED
Question: How to unlock the project?
Tcode /TMWFLOW/PROJ --> System change options
Cross Sys. Obj. Lock -- inacative
By doblecklicking is it unfortunately not possible to activate this function
Question: how to fix this error?
Tcode /TMWFLOW/PROJ --> CTC Status Switches
Warning: The Solution Manager project does not have an active CTS project yet
Question: how to fix this error/warning?
The Solution Manager project does not have an active CTS project yet
Thank you very much!
regards
Thom
Hi,
1.Creation of Task list:
Go to tcode solar_project_admin->system landscape tab->change management tab->create maintenance cycle which will create a task list/maintenance cycle.
2.Before creating the task list go to img project tab,create a project in the development system.
Once the project is properly cretated and task list is created,other errors will be resolved.
Check and Revert back for clarifications.
Regards,
Avinash
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
81 | |
9 | |
9 | |
7 | |
7 | |
6 | |
6 | |
6 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.