CharM Tcode /TMWFLOW/PROJ

Former Member
0 Kudos

Hello!

I have following questions regarding CharM functionality:

Tcode /TMWFLOW/PROJ --> Scheduling --> push "Advance"

or tcode SCMA

I am getting the error "There is no task list for this project"

Question: How can task list be created?

Tcode /TMWFLOW/PROJ --> Project Structure

CTS project --> status in task list LOCKED

Question: How to unlock the project?

Tcode /TMWFLOW/PROJ --> System change options

Cross Sys. Obj. Lock -- inacative

By doblecklicking is it unfortunately not possible to activate this function

Question: how to fix this error?

Tcode /TMWFLOW/PROJ --> CTC Status Switches

Warning: The Solution Manager project does not have an active CTS project yet

Question: how to fix this error/warning?

The Solution Manager project does not have an active CTS project yet

Thank you very much!

regards

Thom

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

1.Creation of Task list:

Go to tcode solar_project_admin->system landscape tab->change management tab->create maintenance cycle which will create a task list/maintenance cycle.

2.Before creating the task list go to img project tab,create a project in the development system.

Once the project is properly cretated and task list is created,other errors will be resolved.

Check and Revert back for clarifications.

Regards,

Avinash