PP members:
What settings do we need to make in<b> MRP</b> to create Automatic Purchase Orders?
Discussions with a friend of mine he was mentioning that we cannot create Automatic Purchase Orders but we can maintain in <b>MRP</b> for <b>Automatic Purchase Requisitions</b>
If we cannot maintain settings <b>Automatic Purchase Orders</b> in <b>MRP</b>, then what are the settings do we need to maintain in <b>MRP</b> for <b>Automatic Purchase Requisitions</b>
Please elucidate on the above
Suren R
Suren,
Directly getting a Purchase order after MRP run is not possible. But SAP provides option to convert PR to PO automatically using ME59N transaction which can be scheduled in background.
Prerequistes for automatic PO creation:
1. Vendor should be enable with automatic purchase order (Purchase data)
2. Material should be enabled with autom PO (Purchasing View)
3. Source List needs to be maintained with preferred vendor as fixed Vendor in the list and also make this record relevant for MRP.
4. Maintain Inforecord for the Material
Now get your planning completed (MRP run), and then use transaction ME59N to create single PO for multiple PR's of a single vendor or any other combination based on the intial screen selection fields.
Hope this helps.... reward your points and close the thread if so,
Regards,
Prasobh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
To create PR, I think you know the settings as our freinds told in this thread...
If you want automatic PO after MRP....you can mark auro PO tick in material master purchasing view for a given plant, which will redude your work soem extent.
please come back if you need more information
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
we can not create <b>purchase orders</b> automatically using MRP run
During MRP run if you want to create Purchase requisations for Procurement type :F you have to specify in MRP control Parameters in create Purchase requisations --1(Create Purchase requisations), if 2 was given it will create Purchase requisations in opening period and after opening period will create Planned Orders.Opening period will be defined using Scheduling Margin Key.
One more thing conversion of Purchase requisations to Purchase order will taken care by Materials Person not by PP person (MRP controller etc), Upto Purchase requisations only we are in Picture..
Regards,
Srihari
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Suren,
In MD02 / MD03 / MD01
you give this value " Purchase Requisitions " in the field Create Purchasse Requistions: ( avoid Planned Orders )
Regards
Krishna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.