BP Relationship - Validity Dates


I am trying to add a relationship to an existing BP, e.g. 'Has SAP account manager'.

In PCUI, I go to the BP, go to 'Relationship', select a relationship. As soon as I enter a Partner ID, the Valid from and Valid to dates gets defaulted to 01.01.0001 and 31.12.9999 and are greyed out so cannot be changed.

If I enter some dates prior to entering the Partner ID, dates get overwritten and warning message appears 'No time constraint: date specification will be ignored'.

The GUI seems to be working in the same way.

Has anyone come across this issue before?




Please check the time dependency settings for the relationship type category in the transaction BUBA. This should help.