Hi,

I am trying to add a relationship to an existing BP, e.g. 'Has SAP account manager'.

In PCUI, I go to the BP, go to 'Relationship', select a relationship. As soon as I enter a Partner ID, the Valid from and Valid to dates gets defaulted to 01.01.0001 and 31.12.9999 and are greyed out so cannot be changed.

If I enter some dates prior to entering the Partner ID, dates get overwritten and warning message appears 'No time constraint: date specification will be ignored'.

The GUI seems to be working in the same way.

Has anyone come across this issue before?

Thanks,

Accepted Solutions (1)

Accepted Solutions (1)

sudheer-tammana
Advisor
Advisor
0 Kudos

Hi,

Please check the time dependency settings for the relationship type category in the transaction BUBA. This should help.

Regards,

Sudheer.