How could I open OB52(table"T001B") for maintenaince on productive system

Former Member
0 Kudos

How could I open OB52(table"T001B") for maintenaince on productive system

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Tina,

Through the transaction SE54 in development environment. Indicate the table, select " Generated Objects " and click on Create/Change. A SCCR key will be asked. Put the key, and select the option " no, or user, recording routine " and save. When you to save, create the change request to be transported between the systems landscape. This solution is going to do with what, even with the environment closed for modifications, it is possible to alter data of this table.

Hope this will solve your problem.

Please regard points.

Regards,

Roger Vier

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

I have also observed some problem with this. But this configuration works.

In SCC4.

Client Role : Production

Change and Transports for Client spcific Objects: NO Changes allowed.

Cross client Object Chnages:No chnages to repository and cross client objects allowed.

-


But if i change the client Role to Test instead of Production , it does not work.

So i keep it as production in our Quality System too.

Award point sif helpful.

Thanks

Tanuj

Former Member
0 Kudos

Change status for client on "Change without automatic recording" for a time in which need to make changes. (scc4)