Capacity Overload issue


in RRP3 if I put Planned order manually w.r.t some demand say on 20.11.2007, it is showing that the order being started on 02.11.2007 (in resource utilization view).

So, the problem is arising is at capacity overload of the resource for 20.11.2007, system is not considering this order.

can anybody suggest any solution? Can send me mail at




Tarit - Where are you looking at this order? The SNP capacity data view? IF that is the case, then the order created in RRP3 will not show up since your order will be an AJ order. Only EE orders would load the SNP capacity view..