on 11-01-2007 7:43 PM
Hi All,
While creating a SC, we got the below error in the Backend application errors.
' SC 1000000222 (P.Req. 4000000011): ME299 Error in commitments check '.
Could some one help us to solve this issue!! Thanks in Advance
Regards,
Antony.
Increase the budget for the Internal order.The error will be solved.
Regards,
Ryan
Edited by: Ryan S on Jun 26, 2008 4:28 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The issue is not related to the internal order (at least I don't think so). The error occurs when the shopping cart is getting transferred over to the backend. The commitment is generated on the backend when the purchase req is created. This is not happening since the transfer cannot take place. If I do the exact same entry on the SAP side, everything is fine (no errors). But, for some reason, the splits on the shopping cart is causing the error to occur.
Budgets are set at the cost center level between operating and non-operating expenses. I checked the available funds and everything looked OK. But, I believe what is happening is that when the shopping cart comes across, the splits are getting rounded causing the amounts to be dramatically different. In the shopping cart world, the user can specify two decimal places. In SAP, it is only one. I asked this question before on how to make them the same.
Monique
This one is a bckend error - Normally if u use an internal order in the SC and when the budget of this order exceeds in the R/3 system...this error appears.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Could some one answer for this..?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
SRM SC does not post a committment in the FI backend which is possible to set up for ECC PR.
at what point of time you are getting this error?
you have follow-on PR or PO?
mostly this message is coming from yr FI budget at backend.
if the figures are not as per yr expectations then you need to take look at GL account.
i.e. whether the GL account derived in SC is correct one for the FI budget or not
BR
Dinesh