Hi All,

I had to add a field from table EKPO to 2lis_02_itm datasource, I did the append structure to MC02M_0ITM straight away and filled in the exit.

Is it the right method or should it have been adding it to MCEKPO? Will it create any problem in delta management?

Thanks a lot in advance.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Seems ok what you did and there should be no problem. Also you may check the guide below.

Regards,

Former Member
0 Kudos

where is the guide?

Former Member
0 Kudos

By guide do you mean BW TAB ?

regards.

Former Member
Former Member
0 Kudos

Hi Rasim,

Say suppose some users change the data for only the new field in the source system, will the data be picked in delta?

Regards.

Former Member
0 Kudos

You need to delete and refill the setup tables then need to do initial load to BW side.