i have in document types for PR's

in transaction code OPTT1 we only one document type NB and require other document types also

can any body help regarding this issue. is there any user exits for this

please help me

with regards

prasanth nara

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

You can use user exits COZF0001 & COZF0002 to achieve more than one document types from PS

Thanks

Kishore

Former Member
0 Kudos

Hi,

Maintain different Document types in T.code OPPR (under External procurement) for Plant and MRP Group. Assign MRP Group in MRP1 view of the material master.