Hi,
Pls advise the step how to get the Milestone trend analysis in Earned value analysis for WBS element and activity.
After assigning the milestone to WBS and activity, iam ticking Trend and earned value indicator and executing the project and iam also giving diff dates in Milestone basic date and acivity confirmation on diff date.
But iam unable to get the curve in T Code CNMT like project is delaying/going as per the schedule.
Pls also advsie any config changes to be made.
Regards
Raju
Hi,
You need to create project version for obtaining milestone trend analysis from your opearative project. In project version configuration it should be considered for milestone trend analysis.
Hope this will help you.
Regards,
Rakesh Pradhan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hai Raju
u can perform milestone trend analysis using CNMT or CJ2B. The method which u r trying is one type. The project versions which u created should hold the dates of the milestones for the different times in the system which again the TrendAnalysis indicator should have been set for the project versions.
Check the versions.
send me the screen shots to solve ur problem
ENJOY SAP PS
Regards
PP
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.