hi all,

is it possible to reffer more than one movement types for a material ,

when inventory user creat manually a reservation with MB21 t-code,

and what is the use of FI indicator on that

thanks in advance

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

hi,

what is the use of retain days in reservation management program ?,

how we know the status of reservation of material ?

whether it is consumed or not?

rgds

Former Member
0 Kudos

Hi Lakshmi,

1.No.

2.It shows that a reservation item is completed.Further goods movements with respect to that reservation item are not anticipated, although they are still possible.

In the case of a partial delivery we can manually set the indicator if no further goods movements are expected with respect to the relevant reservation item.

This indicator is set automatically for a goods movement when the total reserved quantity is delivered.

Regards,

Ramesh

Former Member
0 Kudos

Hi

U can use only single movement while creating Reservation

FI indicator

Check help provided by SAP

Indicates that a reservation item is completed.Further goods movements in respect of this reservation item are not anticipated, although they are still possible. <b> Use</b>

The indicator is set automatically for a goods movement when the total reserved quantity has been withdrawn or delivered. In the case of a partial delivery, you can manually set the indicator if no further goods movements are expected in respect of the relevant reservation item.