Info required on the config for X Plant status

Good morning,

I have been looking at the config for the X Plant status and have come across a field that I need some help on understanding :o)

Mat. Cost Estimate Procedure - we have this set to "Do not cost material; issue error if material component"

What does this mean??

Does this exclude the material from any of the costing runs.

Kind regards,


There are two meaning to this

ex- material A and product B

In the BOM of B, A is assigned as a BOM component

1. Material (A)is not costed at all

2. If the material (A) in question is costed wih error, then give a warning message or error message when costing its product B.

I hope you are clear.

0 View this answer in context