I have been looking at the config for the X Plant status and have come across a field that I need some help on understanding 🐵
Mat. Cost Estimate Procedure - we have this set to "Do not cost material; issue error if material component"
What does this mean??
Does this exclude the material from any of the costing runs.
Kind regards,
There are two meaning to this
ex- material A and product B
In the BOM of B, A is assigned as a BOM component
1. Material (A)is not costed at all
2. If the material (A) in question is costed wih error, then give a warning message or error message when costing its product B.