I have been looking at the config for the X Plant status and have come across a field that I need some help on understanding :o)

Mat. Cost Estimate Procedure - we have this set to "Do not cost material; issue error if material component"

What does this mean??

Does this exclude the material from any of the costing runs.

Kind regards,

Former Member
Former Member replied

There are two meaning to this

ex- material A and product B

In the BOM of B, A is assigned as a BOM component

1. Material (A)is not costed at all

2. If the material (A) in question is costed wih error, then give a warning message or error message when costing its product B.