I have created characteristics, classes. How to link characteristic to configurable material.How to make changes in sale order through OCM.
Regards,
Krishna
Hi Rehman,
Thank you very much
Regards,
Krishna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Krishna,
For Assigning Class & Characteristic to Material is simple,
Go to MM02 select Classification tab
slect the class type "Variants 300" and you get assignment of class screen
select the class which you might have created using CL02 and Characteristics Using CT04
OCM- Order Change Management is a long process:
<u>First</u>:-
In material Master in "workscheduling" tab there is a field "<u>Overall Profile</u>"
you need to maintain it and fill the profile for that particular material to undergo OCM process.
<u>Second:-</u>
The profile has to be maintained in<i><b> SPRO->Production->Shop floor control->Operations-->Change Management for Production Orders --> Define Overall Change profile.</b></i>
Process of OCM:
Tcode CC01 with release key
in object types you need to select "Actv", "object", "MgtRec" and generate a Change Number.
using this Change Number you can change the Object you want to change it
like BOM, Material Master etc.
Then Release the Change Number using Release Key,
You can see the changes in Production Order only after put the "Release Key" in change Number i.e. in CC02.
Then go to <b>COCM</b> Transaction (Order Change Process)
Tick the Change Number and select your change Number & Execute it
Any further detail clarifications you need please write me back
Regards
Rehman
Reward Your Points If Useful
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.