Add field in Confirmation Screen co11N

HI

i want add field in CO11N

1) Break down time

2) Ideal time

3) Change over time

or How can calculated from standard co11n

Former Member
Former Member replied

Yogesh,

Do the following

SPRO

In OP7B,

Create the

Break down time, Ideal time, Change over time as Std value parameters.(copy from SAP001 and name it as Z00001, Z00002, Z00003 resp. and change the description to Break down time, Ideal time, Change over time.

In OP19

Create a new std value key as Z000 copying from SAP1 and assign the above created SV parameter in position 4,5,6.

In work centre

Assign this std value key- Z000 in basic data.

Now create routing and see that this work center is assigned to operation where you want to assign the Break down time, Ideal time, Change over time.

Now create a order and release it.

Goto CO11n and see, you will get these fileds where you can enter the data and save it.

please come back if required.

0 View this answer in context