Hi experts,
In repetitive mfg, we want to plan a component which is sometimes made in-house or procured from vednor.
Hence, for the component, we want to get planned oder for total requirement.
The same planned order can be convertable to Pur request or can be used for REM GR posting.
Request to guide.
Regards
Nitin
Hi Nitin,
you cannot convert planned order to Pur req/ Prod .order in REM , since it has PE order Type. In your case, u want to use same planned order for Both inhouse and external, it is also not possible.
if you know, how much percentage in total requirement , to be produced in Inhouse and External , u can create two production versions and use quota Arrangement.
u can assign procurement type and percentage for each production version.
MRP run create both planned order and pur requistion as per percentage has given.
other wise u have to create Pur req manullay.
please come back if required more details.
regards
pradeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Nitin,
In case of REM ,you must be aware the Planned Orders are of 'PE' type i.e they can not be converted.If you want to use procurement type'X',the you need to maintain quota for external /inhouse.so, that accordingly Planned order(for Inhouse) & purchase Req. for external will be created.If it is not defined then u need to create purchase order or purchase req. manually as & when reqd.
Points if found useful
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.