on 10-30-2007 4:44 PM
How can I upload budget in cost centers? What are steps involved?
Thanks,
<a href="https://wiki.sdn.sap.com/wiki/download/attachments/52006/Costcenterexcelupload1.jpg?version=1">Refer to my wiki posting 1 of 5 !</a>
<a href="https://wiki.sdn.sap.com/wiki/download/attachments/52006/Costcenterexcelupload2.jpg?version=1">Refer to my wiki posting 2 of 5!</a>
<a href="https://wiki.sdn.sap.com/wiki/download/attachments/52006/Costcenterexcelupload3.jpg?version=1">Refer to my wiki posting 3 of 5 !</a>
<a href="https://wiki.sdn.sap.com/wiki/download/attachments/52006/Costcenterexcelupload4.jpg?version=1">Refer to my wiki posting 4 of 5 !</a>
[url=https://wiki.sdn.sap.com/wiki/download/attachments/52006/Costcenterexcelupload5.jpg?version=1]Refer to my wiki posting 5 of 5 ![/url]
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You have to prepare the budget file using the cost center/ cost element combination. You can develop LSMW to upload and if u can u can manually do it in KP06.
assign points if helpful
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.