on 10-30-2007 2:08 PM
hi,
We have a new ECC6.0 system. the Sales order and delivery pulls into the Stock requirements list, however the document numbers donot pull into the MRP Element field. Any idea how to solve this
Checking Group for Availability Check governs if the requirements are captured at document level or clubbed together into daily requirement.
So check the Checking group assigned in your system. 01 is daily reqt, 02 is individual reqt.
Ashutosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Run MRP with material in Transaction MD02 and check
Regards
Ramesh