Clarification on CVC creation

Hi,

I tried creating CVC using MC62 for a single product .

I get a message background job is succesfully schduled . The job is also completed but CVC are not created.

What i identified is the particular product is not available in product master.

Is it mandatory that all product should be created in product master before creating a CVC ?

Regards

BVN

Former Member
Former Member replied

Valavan,

Check the following in /SAPAPO/MC62.

Select button "Create Characteristic Combinations" and see if Adjust Time Series Objects and Switch On Implemented BAdi are checked under Action Selection. Uncheck them.

Also all the options under Check Selection esp Check SCM Master Data.

Then try creating one CVC manually.

It should allow you to create the CVC successfully.

Remember to generate the according Planning Area Time Series - then only the CVC will be available for Interactive Planning.

There is no need to do realignment to create just one CVC. It is too much work.

Hope this helps.

Somnath