on 10-30-2007 10:52 AM
Hi all,
Can anyone throw some light on where do we assign profit center in Material master?
thnx
Shravan
You need a profit center and it must be assign into material master at sales:general data view
http://help.sap.com/saphelp_ides/helpdata/en/b7/c43a289d5411d189b60000e829fbbd/content.htm
hope this helps.
pls assign points as way to say thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Shravan the following configuration steps may useful to u
3 Configuration
3.1 Master Data
3.1.1 KA01 Create Additional Cost Elements - New
Use
Create all cost elements manually as described below.
Prerequisites
The accounts for these cost elements already exist in the company code. This has been configured by installing the Core Financial Accounting building block.
Procedure
1. Access the activity using one of the following navigation options:
IMG Menu Controlling  Cost Center Accounting  Master Data  Cost Elements  Individual Processing  Create Primary Cost Element
Transaction Code KA01
2. Activities: Enter cost element key and valid-from and valid-to date, then click button Master data and enter remaining data. Then choose Save.
Give me points if u satisfied...
Dasharathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Ravi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.