on 10-30-2007 3:10 AM
Hi Friends,
I am using one key figure, SF, to store system generated statistical forecast. Every month this forecast is generated and versions I can see in forecast comparison report. That is fine. But market intelligence and some other stuff is added to this SF key figure and Final Forecast FF is reached. This is calculated using macro.
Is there anyway forecast version of Final Forecast (FF) can be stored and compared using standard feature of demand planning (APO 4.0)?
MM
Hi MM.
A simple approach would be to use a key figure (say "Previous FF"). Using a macro, copy FF to Previous FF before generating new forecast.
Hope this helps.
M