Can U Please explain when to use CO19 transaction

Thanks and Regards,



The Order - Operation normally has stages of Set up , Processing, Teardown activities and different Capacities / Resources may be needed for these activities. CO19 helps tracking the progress of individual 'EVENTS' of an Opration, thus tracking Capacity Requirements / Output at a finer / more detailed level. It also makes posting the Confirmations a simpler process : which can be set up with appropriate MES Interface. I hope this clarifies the subject.