on 10-29-2007 3:25 PM
Hi Friends,
As you know in repair order we would use following steps
create contract va41.
create service notification with ref to contract (IW54)
create repair order (IW59)
create return delivery (VL01N)
create order (VA01) then after creating on repair
& while confirming copy item proposal message I am getting error as "<b>No entry for the plant M110 service object 01- 1699 (this is service mate) in table T399A".</b>
Ple suggest solution.
Thanks
Shiv
The steps you have mentioned is not fully correct. But anyway the cause of your error is that you need to maintain service product details in transaction OISD.
B A
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for clarification.
Now as you advised to specify all fields in OISD, I am not getting fields in dropdown list like Task list group, Group counter, Task list type, Reference type, Technical object reference type etc.
<b>Ple guide me how to create these field</b>. Are these field created by SD or PP consultant?
Thanks
Shiv.
hi,
chek this table in se16. its a config table.luks like you have missed some config.
saurabh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
did you create the material in the particular plant? Do you have any serial number / equipment number for the material, if yes, check for the palnt of the same.
Prase
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.