Hi All,
I am testing one scenario in ECC 6.0, Here i have given labour, machine & setup time as 600 min each. Now i create & release order having only one operation with controll key PP03. As i am testing for demo I immediately confirm order by co11n but at time of confirmation when i clicks on ACUAL DATA tab only order qty. is coming , No activity times are coming So please tell setting for this. Now in this situation I manually entres values for setup, machine and labour time and confirms the opeartion.Now after confirmation when i checks operation in order it shows same time as actual start time and actual finish time.
My objective is to get different timing between opeartion start and operation finish time though i creates & confirms order immediately i.e. syastem should show me diff timing based on activity time entered.
Your earlist replies will be appreciated.
Thanks in advance
Sachin.
Jadhav,
Note your work center which you are using in the routing
In Tcode CR02 & Go to the costing view of this work center-Check whether you have maintained the activity type for Set Up,Machine & Labour
If not then that is the reason why you are not getting the values even after pressing the A Actual Data button
Maintain activity types for them
you have to assign activity types to a cost center
Assign that cost center to the work center
Then you select the activity type for each activity & assign the corresponding formula
TCodes
For Creating Cost Center-KA01
For creating Activity Types-KL01
For Assigning Activity type to cost center-KP26
Revert back in case of any doubts
Reward points if useful
Regards,
SVP
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear SVP,
I appreciate your initiative in helping out Mr.Sachin,but dont copy my answer and
paste it as an solution.Morover its not relevant to his problem.
He has asked what setting's are missing as he could not see the activity times
shown automatically in CO11N screen automatically after entering the production
order number and operation number.
Regards
Mangal
Dear Mangalraj,
I admit that iam new to SAP,but let me be frank with you,I didn't copied this from any where,I typed on my own,I don't want to take others credit
Coming to the actual query
if we don't maintain the relative activity type for the activities,I think we wont get the actual activity time automatically in CO11N screen
I myself faced this problem
Regards
SVP
Hi SVP,
i will try as per your suggestion, But more in deep as activity timings are not coming based on routing values by clicking on ACTUAL DATA tab i manually enterd these values during operation confirmation. Now even though i have entered these values during confirmation these are not getting reflected in Actual Start & Finish time of operation in operation overview in order after confirmation.Could you highlight on this .
Thanking You
Sachin
Sachin,
If you need to capture excat timings of operation start and finish etc.... you need to confirm through even based confirmation transaction CO19.
Regards,
Prasobh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Prasobh,
My query is to get all timing mentioned in routing for calculation of Actul start & finish time of operaion all irrespective of that actual ime of confirmation.i.e. system should show me Actul tart & finish time of operaion based on values maintained in routing
Thanks & Regards
Sachin Jadhav