u0093Delivery does not existu0094 while doing PGI confirmation.

Former Member
0 Kudos

Hi everybody,

We are receiving IDOC to create Picking confirmation and PGI

IDOC used: SDPIID01, Message type: SDPICK & Process code: SDPI

When ever we ACTIVATE the IDOC user-exit’s project we are getting error

“Delivery does not exist”

Even there is no coding at the user-exit still we are getting this error.

Once we DEACTIVATE the user-exit’s project it is working correctly and PCI is created.

As per our business requirement we may need to use this user-exit to do some basic data manipulation.

Enhancement using : VMDE0003

User exit using : EXIT_SAPLVMDE_003

Project (custom) : AU3_NZ3

Package (custom) : Z001

Please advise if any one faced the same issue or let me know whether I doing anything wrong while activating the project?

Appreciate if you could reply ASAP. Thanks.

With Regards,

Ashwin

2 REPLIES 2

Former Member
0 Kudos

The problem cannot be solved and hence we have removed the user exit and now its workig

With Regards

Ashwin

0 Kudos

SAP note 49361.

Place E_VBKOK = I_VBKOK in the user exit.