Hi Gurus,
I want to know to what extent SAP R/3 supports for capacity planning?
what are the pre-requisites for that ?
How overloading of work center is handeled in a production order?
please reply for the problem.
Thanks
GNK
Hi
For Making capacity Planning, u have to do the following Configurations
1) Define time units
Path : SPRO Production  Capacity Requirements planning 
Master Data  Define Time units (OPCF)
2) Define Capacity Category
Path : SPRO Production Capacity Requirements planning Master Data Capacity Data Define Capacity category.
3) Set up Capacity Planner.
Path : SPRO Production Capacity Requirements planning  Master Data Capacity Data  Set up Capacity Planner
4) Define parameters
Path : SPRO  Production Capacity Requirements planning  Master Data Work Center Data Standard value  Define Parameters (OP7B)
5)Define Move time matrix.
Path : SPRO  Production  Capacity Requirements Planning  Master Data Work Center Data  Define Move time Matrix (OPCN)
6) Define Setup matrix.
Path : SPRO  Production  Capacity Requirements Planning  Master Data  Routing data  Define Setup Time Matrix
7)Define Control Key.
Path : SPRO  Production  Capacity Requirements Planning  Master Data  Routing data  Define Control Key(OPCG)
😎 Define Shift Sequence.
Path : SPRO  Production  Capacity Requirements Planning  Operations  Define Shift Sequences (OP4A)
9) Define Key for performance efficiency rate.
Path : SPRO Production  Capacity Requirements Planning  Operations  Available Capacity  Define Key Performance Efficiency Rate (OPDU)
11) Specify Scheduling type.
Path : SPRO Production  Capacity requirements Planning  Operations  Scheduling  Specify Scheduling Type (OPJN)
12) Set up Production scheduler group.
Path : SPRO Production  Capacity requirements Planning  Operations  Scheduling  Set up Production Scheduler Group (OPCH)
13) Select Automatically.
Path : SPRO  Production  Capacity Requirements Planning  Operations  Scheduling  Task List Type  Select Automatically (OPJF)
14) Define Scheduling parameters for Production orders.
Path : SPRO  Production  Capacity Requirements Planning  Operations  Scheduling  Define Scheduling Parameters for Production orders (OPU3)
15) Define Scheduling parameters for networks.
Spro ProductionCapacity requirements planningOperationsScheduling Define Scheduling Parameters for networks
16) Define Reduction Strategies planned/ production orders.
Spro ProductionCapacity reqirements planningoperationsSchedulingReduction strategiesDefine reduction strategies planned-/production order
17) Define Reduction Strategies for network/process orders.
Spro ProductionCapacity reqirements planningoperationsSchedulingReduction strategies Define reduction strategies for network/process order
18) Define Selection profile.
SproProductionCapacity requirements Planning EvalutionProfiles Define selection profiles
Reward Points,if Usefull
Regards
Palaniappan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Jain,
please send me the screen shots of capacity planning to my mail id
mohan.gatiganti@gmail.com.
regards
madan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please send that document to vadlapatlap@yahoo.com
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi send me u mail id i will send u screen shopts.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.