on 10-26-2007 1:12 PM
Dear All,
When I try to post a transaction in f-02, asking Controlling area not maintained.
what are the settings need to be done, i.e posting a transaction in f-02 without maintaining Controlling area.
Regards,
Hari.
Hi,
You do not require to maintain a controlling area to post a document using F-02.
If you are maintaining a controlling area and that you have created cost elements then system will ask you to mention cost object for all P&L items you post using F-02
Thank you,
Ramesh.