on 10-26-2007 10:32 AM
hi,
i got an issue to configure finished product which is given for packing and labelling to a sub contractor and sent back to me and i will sell the same.
i dont know whether this process can be configured or not.
if configured -
any body can give me guidelines related to that.
if not possible to configure why it is not possible in std sap.
can you plz explain on this.
regards,
balaji.t
hi
There is a subcontracting process in SAP (But basically it is related to MM).
In this we create a PO with Subcontacting Indicator C . Then delivery and GI.
when the Goods are return we go MIRO and GR .
Hope this help.
But i will suggest MM consultants can give detail answer to ur question
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Said scenario can be mapped but it is integration of MM & PP module,
Subcontracting scenario is involved. pls discuss with your team mates. I think from sd no any special confiuration.
Regards,
Veeresh babu M
forum points if helpful
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Agree with Kaustubh,
You can use subcontracting in MM for this, better you can consult with an MM person.
Prase
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.