cancel
Showing results for 
Search instead for 
Did you mean: 

Sp.Procurement key 40 stock transfer order.

Former Member
0 Kudos

Hi Friends,

I am facing typical probelm in post go live stage of the project .

Scenario : 2 plants say 'A ' & 'B' both are producing product 'x'. this product contains dependent componenets 'y' it is onle produced in plant A.

Hence sp.procurement key 40 (stock transfer order) is maintained in plant B for component y .

MRP runs monthly once.

Storage location stock excluded from MRP run

Pur req cretaed in in nplant B and planned order in palnt A.

Pur req converted in to number Purchase orders (PO items) partialy.daily arround 20 Purchase orders are created,

Now th problem is while carring out MRP run for next month system considers the open PO items while caluclating requiremnt of y

My requirement is that system should not consider open PO , it should give gross requiremnt of Y depending upon PIR ;s of x.

Stratgey 11 is mainatined for x in both plants

Regards

Sandeep

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Sandeep,

I think if the storage location in the open is the same as storage location which is not planned then open PO's should not be considered.

Regards

Vineet

Former Member
0 Kudos

Hi

You have to run total planning & configure scope of planning.

accordingly run MRP not for single plant.

Further please follow the following link which is self explanatory.

http://help.sap.com/erp2005_ehp_02/helpdata/en/f4/7d3f9344af11d182b40000e829fbfe/frameset.htm

In the above link it is clearly explained as to what procure ment types to be maintained.

Pl. follow the same.

Also run MRP for scope of planning.

Regards

YMREDDY