on 10-25-2007 4:22 PM
hi,
how to set-up inter-plant sub-contracting.
from plant-1 materials will be sent to plant 2.
In plant -2 processing will be done and send back the finished goods along with scrap if any to plant-1.
pl explain the scenario in detail - step by step (with T,codes) if u know the solution.
thanks
mohan
In plant A for material M1 (finish) define with special procurement key (stock transfer from plant B) in MRP2 view from plant B. (If it is MRP relevant)
I am sure you know the config of Stock transfer
Create the sub contracting PO as like out side vendor for plant B (make sure you have created the Plant B as vendor also and plant A is customer also and all config has been done for STO.) with second line item for the scrap if you are systematically do otherwise just receive with 501 movement
Then follow the same process as regular sub contracting process
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.