on 10-25-2007 3:23 PM
Hi
I am able to release the schedule lines in ME84.But still when I go in MIGO the message displayed is document contains no selectable items.
Is there any step remaining?
Regards
This problem was resolved after creation of release profile and defining new output type
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Please check the delivery date in schedulig lines. Before del date GR will not happen.
For example if del date in SL is 29 oct and you are preparing GR on 26 oct , std sys will not allow this.
(depends on config)
Solution is to change the delivery date in SL to GR date.
Check and confirm
Kedar Kulkarni
Message was edited by:
KEDAR KULKARNI
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
This is not related with schedule dates as the schedue is on 24th October and I am preparing GR on 27th October.
So this issue is not related with SA dates.
Also I checked if there is any confirmation control key,it is not there.
Still if I go to create Inbound delivery there is error message that no inbound deelivery can be created as this item is not subjected to confirmation.
Any other suces of error?
Regards
Vaibhav
Hi
No.
But check the following,
1.Is there any Confirmation control for this line item
2.Item is not blocked
3.Check delivery date is same as that of document date/Posting date.
4. Ensure some open quantities are available for GR
hope this helps you
Regards,
Sasi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.