on 10-25-2007 11:54 AM
EXPERTS:-
1. what is the Base line confuguration, and Final configuration.
2. what is the difference between automative testing, and integratin testing.
Hi Ameer,
When you start configuration you do it in 2 phases one is Baseline configuration and other is final configuration
In baseine Config you setup all Enterprise structure
Creation of cocode, Businses area, and all orgn units for all modules
Final configuration: you configure the business process based on the above organizantinal units.
Intergaratin Testing means testing done across modules exampel
Purchase to Pay scenaro
MM and FI integargtion
Sales to Cash
SD -MM- FI integarrion
All the scenarios will be tested and accounting enteris will be verified
Best Regards
Ashish Jain
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.