Hi All,

Commitment costs are raised by issuing PR's & PO's.

Can you tell me how Actual costs are raised in projects,please mention all cases.

Muzamil

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Actual costs are posted in prject in /and from a host of sources:

1.Confirmation of activities

2.Goods Receipt against account assigned purchase orders / service orders

3.Goods Issue against project reservations

3.Confirmation of account assigned orders

4.Settlement

5.Transfer posting

Regards

Muraleedharan.R

091 9880028904

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

Actual Cost are raised whn the commitments are realized i.e. Goods reciept/invoice reciept made. In case of internal activity there wont be any commitment it will become actual when it is confirmed. Goods Issue against project reservations also makes actual postings. Settelement and transfer posting leads to actuals.

Regards

Murali

Former Member
0 Kudos

Hi,

On releasing PR/PO of materials the same will come as committment and on goods receipt of the materials, the same will become actual cost of the project in case of externally procured materials.

Regards,

Rakesh Pradhan

Former Member
0 Kudos

Hi,

Confirmation of commitments (ie goods issue in case of PO) results in actual costs. Apart from this, confirmation of activity also results in actual cost provided the activity carries planned cost.

Reward points if useful.

Regards