I need to deliver project related material thro' PS outbound delivery.

currently after the production is complete for a specific project material, end user is using moment type 281 to issue the project stock to the network.

i've suggested them to do PS delivery so that movement type 281 is not necessary.........i'm i right with my suggession.

regards,

Sudeer

Accepted Solutions (0)

Answers (1)

Answers (1)

philippe_marque
Active Participant
0 Kudos

Hi,

With PS, delivery will be created with transaction CNS0 and movement type will also be 281 ...

If you did the goods entry, you need to do one day the goods issue and movement will be 281.

So, you are wrong ...