My user has worngly capitalize the asset in wrong month oct,2007. after that he also reverse the document. but when capitalize the asset in sep,2007, system maitain the capitalization date for the month of oct. but he wants the system should adopt the capitalization date for the month of september.
is there any way to change the capitalization date etc.. or any other...
spro->asset accoutning->master data->screen layout->Define screen layout for asset master data
Select the screen layout for the asset class under which your asset is, and in logical field groups, selected log grp 2 (Posting information)
and then in field group rules, change the capitalization date option from Display to what u want
or even to particular asset u can change in AS02
Assign points if useful
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Amit I changed a capitalization date from a asset a few days before, I changed capitalization date in general data tab, and in valuation tab I change the value of field "depreciation begin", the asset is working as expected.
when I chaged the value for "depreciation begin" SAP updated automatically the future projection of depreciation.
Capitalized Date can be changed via AS02. Isn't this allowed in your company settings?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.