We are using SEM-BW 4.0, SAP-BW 3.5, running BCS. We are trying to change the Breakdown Category of an FS Item going forward. The system allows to change and save the Breakdown Category as needed, but when we attempt to post a manual entry or run the data stream or any tasks, the BCS system crashes with the following error:

Transaction: UCWB_INT

<b>Can we change the break down category like this mid wasy as changed by Shiva.</b>

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

You should never change the break down category midway. Break down category is similar to a field status group in R/3. Though it will not throw any error when you are saving ,subsequently it will cause inconsistency since the already posted items will be looking for the changed objects. Say for example you are making change to a Functional area as required item for a FS item for which data has already been posted. When you are posting an item, system will look for this object even for the items which were posted earlier which results in inconsistency. If the changes are absolutely required then you need to run a program which will allow you to make changes the posted data earlier. Hope this is lear now.

dan_sullivan
Active Contributor
0 Kudos

When a change to a breakdown category is needed, the BCS configuration for master data has a program "Breakdown Check" which checks records for inconsistencies and provides a means of updating the records, automatically in some cases and manually in other cases, to meet the requirements of the new breakdown category.

Former Member
0 Kudos

Hi dans, we've spoken before on sapfans (TheScotsman) I have encountered a situation with several thousand inconsistent records, the problem is that the breakdown check selection only allows item and year

but if there are eg 15 records for one item then the subassignment values (eg partner unit) that the client wants could well be different for each record.

Any idea how to enter multiple values for each occurence of the same item?

dan_sullivan
Active Contributor
0 Kudos

One suggestion is to assign a value in the breakdown check program and subsequently post entries to the correct values either in BCS or the source ledger.