PR not CIFed to R/3


I am not getting R/3 Purchase requestion number in APO when i am using stock transfer with rule based in PPDS.I have done the settings as per SAP help.

1)PP planning procedure-5 MLATP

2)general setting-External procurement always transfer

3)Publication maintained.

4)R/3 both the plants have been maintained with spl.proc.indicator in Material master

5)Integration model i have activated PR and PO radio button for the plant and material

Still i am not getting...