on 10-24-2007 12:01 PM
Dear PM Guys,
I never done activity based costing through WC in previous proj.As a PM guy what is exactly my part and CO guy part in Customizing and while assigning of one or more activity types in Maint.Work center.If there is any detailed note .I request you guys to send it to my mail ISWARI_BABU@YAHOO.COM.Thanks in advance.
Regards
ISWARI
Mr Thiyagarajan & Mr Vinay,
This may be my last query in this particular thread.
If I assign 2 activities to one cost center in KP26 and assign only one activity in workcenter with formula sap008(costing tab bottom fields),then also i can able to get labour cost for both activity if i use in operation of MO which contains the particular WC.
Eg
In KP26
Activity-TECH and Activity-TECHHELPER assigned to CC-20000
In IR02
WC-INTECH
Costing tab
CC-20000
TECH and SAP008 is assigned
In this condition Iam able to use both activity types in Operations of MO and in cost tab of MO, iam getting cost of TECH hours and TECHHELPER hours.
Is it correct.
Regards
ISWARI
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Thiyagarajan & Vinay,
I got it around 75% based on yours input .The issue is
My standard value key is SAP0,CAPACITIES tab other formula is SAP008,SCHEDULING tab other formula is SAP004 .
In costing tab if I assign ACTIVITY and FORMULA in bottom(ie single entry)
its working fine and its reflecting in the cost tab of MO.
Eg Activity-TECH(Technician) and Formula SAP008
The requirement is I want to specify 2 activity type in the same workcenter and while creating order,the user will select the activity type which they want.
(Eg ACTIVITY -TECH and TECHHELPER and both are assigned to same cost center and cost element and the diff is only rate/hour)
How to do this?pl help
regards
ISWARI
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi iswari
yes you can create 2 activity for one work center,but the problem is it will not be as selectable , it will ask to specify the work for the acticity( like in production order we specfiy as setup,labour and machine) .
for acheiving this you have to create standard values consist of your parameters in customization ( for parameter OP7B and standard value OIZ2) and specify in the respective work center and also formulas will be different. if you have PP consultant kindly consult with him regarding the workcenter
And plan for that activity
regards
thyagarajan
Hi Iswari........
Is you question, most of the portion is related with FICO......
You have to first decide what are the activity cost you hvae to capture........mostly it is Labour Hour rate, Machine Hour rate, Set Up Time, but from PM point of view it is only Labour Cost. Then for these Activity types, your finance guy will create a Cost element which he will assign to your Activity Type & will give hour rate for this Activity.
After this you have to asssign this Activity type to your Work Center in Costing tab.......other than this you have to remember that Formula Key u r using is SAP008 for PM, here you can put the formula but generally in PM it is used as standard.
Hope this will help..........
Regards............
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi iswari
first create Activity type ( specify the cost element) and cost center
Plan for activity and cost center( KP26)
Create forumla and dependent parametes( customization)
Create work center( here you have to specify the activity and cost center and
formula)
specify the work center in equipment
then if you create the order fo the equipment cost will be calculated
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.