Hai All,
I need assistent for the below requirement.
Let me expalin tha scenorio
For a particular material I am having 10 open orders i.e yet to be delivered.
based on the open order only we procure material from outside. Problem is when I do the GR to my plant the system automatically allocates the quantity to open orders which i don't want. since it is a rare material i want to dopartial delvery.
I dont know where to control this
Kindly assist me in this regard
Regards
Saru
you can do rescheduling or MB21 for allocation of mat to cust