Hai All,

I need assistent for the below requirement.

Let me expalin tha scenorio

For a particular material I am having 10 open orders i.e yet to be delivered.

based on the open order only we procure material from outside. Problem is when I do the GR to my plant the system automatically allocates the quantity to open orders which i don't want. since it is a rare material i want to dopartial delvery.

I dont know where to control this

Kindly assist me in this regard

Regards

Saru

Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

you can do rescheduling or MB21 for allocation of mat to cust