Dear All,
The Client is using Factory Calender which is assign to Planing Profile.
Saturday and Sunday is marked as Holiday in Factory Calender, they want
only 1st and 4th Saturday as holiday. I have checked in SCAL T.code,
but i need to modify that can you please help me how & where to modify.
Thanks in Advance
Regards'
Syed
Hi Syed,
You can try creating a Special rule <OR> you should go to particular year and change the Non-Working Days to Working Days manually & save it.
Regards
Rehman
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Rehman,
Thanks for your valuable advise. I have to enter the alternate data Manually to close the issue.
Points Awarded.
Regards'
Syed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.