Hi,

SRM 5.0 - Classic Scenario

User U-1 is under the company code C-1

Shopping Cart SC-1 has been created successfully for the Product Category PC-1

Product Category PC-1 has been assigned to Purchasing Org. POrg-1

<b>Question 1)</b>

But back-end POrg-1 has NOT been assigned to Company Code C-1. What will happen to this SC-1 ? Will the PO be created ?

<b>Question 2)</b>

Next....Vendor V-1 has been assigned as Source for the Shopping Cart SC-1.But Vendor V-1 has NOT been extended to the Purchasing Org POrg-1. But it has been extended to the POrg-2.

Will the above SC-1 will be converted as PO ?

Please help. Currently I am doing blueprint. I don't have the system to do the above test.

With regards,

Pranav

Former Member
Former Member replied

Hi Pranav,

Here are answers to your questions;

Question 1)

But back-end POrg-1 has NOT been assigned to Company Code C-1. What will happen to this SC-1 ? Will the PO be created ?

<b>

Sundeep: No, This PO will be in "Error in Transmission" with a backend application error for a PO. Same as trying to create it directly in ECC, it will error</b>

Question 2)

Next....Vendor V-1 has been assigned as Source for the Shopping Cart SC-1.But Vendor V-1 has NOT been extended to the Purchasing Org POrg-1. But it has been extended to the POrg-2.

Will the above SC-1 will be converted as PO ?

<b>Sundeep: No, it is same as trying to create a PO in ECC directly, it will not allow you to create it. Also this scenario is not practical, as in reality, when you replicate vendors from a backend, it will replicate all Porgs that the vendor is created with, hence this scenario concern is ruled out !</b>

Thanks,