Do I need a CTS project for Urgent Corrections?

Former Member
0 Kudos

I am trying to configure CHARM in a simple way to allow us to move transports across one CRM landscape using the Urgent Correction process.

I have been through all the config & created a maintenance project which appears to be ok when checking with /tmwflow/charmchk.

The status of this in solar_project_admin is "New". I'm not sure if that needs to be anything different, but I can't see where to change that status if required.

However, when I go to tcode tmwflow/maintinst to try to create a maintenance cycle for the project, no projects for maintenance appear in the list.

Am I missing something? I've not made any CTS settings, as I don't want to synchronise any IMG work across different systems.

Does anyone know what I'm doing wrong?

Thanks

Mark

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Mark,

Did you activate Change Request Management for the project? (under systems landscape--> change requests tab in SOLAR_PROJECT_ADMIN)

Regards,

Kriti Bhalla.

Former Member
0 Kudos

Kriti

Yes change Request Management is activated.

I haven't clicked on the button below to create a task list yet.

Mark

Former Member
0 Kudos

I resolved the problem.

We found that when you switch CTC = 1 on TMS in the satellite system, it then requires TMS to be reconfugred to be client dependent.

The project now appears in the list.

Thanks

Mark