BOM assign to WBSE

Former Member
0 Kudos

Dear All

Kindly any one tell me how I can assign BOM to respective WBSE.

Thanks in Advance

regards

sujit chanpura

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

The transaction for creating WBS BOM is CS71, if that is what you are looking for.You need to enter your WBS No, Material No, Plant, BOM usage and change number in this transaction. Transaction for taking change number is CC01.

Further, If you want to transfer a BOM to a network activity, use trasaction CN33. For this certain customization settings need to be made - Project system --> Materials -->Bill of material transfer >Define profiles for BOM transfer,>Define reference points for BOM transfer etc.

Hope this answers your question.

Muraleedharan.R

091 9880028904

Former Member
0 Kudos

Dear Sujit

U can maintain WBS BOM, check the following link

http://help.sap.com/erp2005_ehp_02/helpdata/en/cd/a39838cc67f51be10000009b38f8cf/frameset.htm

Regards

Murali

Former Member
0 Kudos

Sujit,

Check this. All about matrial & BOM for PS.

http://help.sap.com/saphelp_47x200/helpdata/en/d7/b8853488601e33e10000009b38f83b/frameset.htm

Hope it helps.

Thanks,

PJ