on 10-23-2007 8:55 AM
I need to do budget control by cost center. But I cannot find how to link the fund center to cost center. Could you please tell me ? Thank you!
I don;t know which version u are using for the funds management.
please follow the the following for assiging the fund centre to cost centre for budget control.
1-first make sure the funds management is active & your avaliability control is also active.
2-In vesrion 4.6 you can assign the cost centre to fund center by using the transaction FRC3
3-in the Ecc6 you can define ur derivation startegy in the system or may be u can use the standard available derivation stategy. the assign the cost centre & fund Centre Relationship
for you further information, please go through.
http://help.sap.com/erp2005_ehp_02/helpdata/en/f0/ca5716260211d28a430000e829fbbd/frameset.htm
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you very much!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.