budget control

Former Member
0 Kudos

I need to do budget control by cost center. But I cannot find how to link the fund center to cost center. Could you please tell me ? Thank you!

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

I don;t know which version u are using for the funds management.

please follow the the following for assiging the fund centre to cost centre for budget control.

1-first make sure the funds management is active & your avaliability control is also active.

2-In vesrion 4.6 you can assign the cost centre to fund center by using the transaction FRC3

3-in the Ecc6 you can define ur derivation startegy in the system or may be u can use the standard available derivation stategy. the assign the cost centre & fund Centre Relationship

for you further information, please go through.

http://help.sap.com/erp2005_ehp_02/helpdata/en/f0/ca5716260211d28a430000e829fbbd/frameset.htm

Former Member
0 Kudos

Thank you very much! Your point is very helpful for me and I will try it again.

Answers (1)

Answers (1)

Former Member
0 Kudos

Thank you very much!

Former Member
0 Kudos

Done.