Dear Gurus,

Expertise is required.

Can we carry out transport planning or creation of shipment document after the goods issue.

Once all despatches done can we carry out the shipments documents at the end of the day.

This will really very helpful to us.

Please extend ur help for this.

Thanks

Rgds,

Saurabh

Accepted Solutions (1)

Accepted Solutions (1)

reazuddin_md
Active Contributor
0 Kudos

Hi Saurabh,

have seen all the replies for this post,

but in my project.

we r currently creating shipment doc's ( VT01n, VT04 ) after doing PGI only.

I guess, there is background config might be there to set up this

before PGI , after PGI.

It depends ,that if the transportation client using is of third party. then after PGI i assume will create Shipment doc's which we r doing currently for our project.

let me know for any inputs,

Former Member
0 Kudos

Hi,

Thanks . Here in my case i want to do shipment costing after PGI is done at the end of the day. Our despatches r continous so i can not do PGI at the end of the day & then shipment costing.

Please let me know if any specific customising is there.

Rgds

Saurabh

Former Member
0 Kudos

Hi Suarabh

Yes customization is there. U can do that process after PGI

Regards

Former Member
0 Kudos

Dear Sir,

Please let me know the Customisation for the same.

Rgds,

Saurabh

Answers (3)

Answers (3)

Manoj_Mahajan78
Active Contributor
0 Kudos

Saurabh,

Generally process is-

1)VL01N

2)VT01

3)VL02N-PGI

4)VI01

5)ML81N

6)MIRO..

Shipping docs (VT01) are created before PGI...

REWARD IF THIS HELPS...

Regds

MM

Former Member
0 Kudos

Hi Saurabh,

You cannot carry out transportation planning or creation of shipment after the goods issue has been executed. Once goods issue is done it means that the material has left your premises so there is no need for a transportation planning after it.

In case you need carry out the shipment documents at the end of the day you could just create the delivery doucments during the day and at end of the day create the shipment documents and the goods issue.

Regards

Nadarajah Pratheb

Former Member
0 Kudos

Hi,

you cannot create a shipment document for the delivery whos PGI is been done.

You will have to skip PGI if you want to carry out shipments at the EOD.

Regards

Abhilash.