Hi SAP Guru,
I have a problem with the report S_ALR_87013558. I have some commitments(PR/PO) and some partial GR (not fully GR), then user want to close the PO. Why the value goes to Remaining order plan? I wish it can go to the available budget. Plz advice regarding this issue. I have searched all over in customizing and cannot find where these settings are done.
Help here will really be appreciated
Before force close :
Budget Actual Commitment RemOrdPlan Assigned Available
4500 3877 54 0 3931 569
After Force Close
Budget Actual Commitment RemOrdPlan Assigned Available
4500 3877 0 54 3931 569
Regards,
Nies