Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

PR/PP : Commitment vs. Rem Order Plan (report S_ALR_87013558)

Hi SAP Guru,

I have a problem with the report S_ALR_87013558. I have some commitments(PR/PO) and some partial GR (not fully GR), then user want to close the PO. Why the value goes to Remaining order plan? I wish it can go to the available budget. Plz advice regarding this issue. I have searched all over in customizing and cannot find where these settings are done.

Help here will really be appreciated

Before force close :

Budget Actual Commitment RemOrdPlan Assigned Available

4500 3877 54 0 3931 569

After Force Close

Budget Actual Commitment RemOrdPlan Assigned Available

4500 3877 0 54 3931 569

Regards,

Nies

Former Member
Not what you were looking for? View more on this topic or Ask a question