hi,
when sales order created for individual requirements it automatically creates P.R and this P.R is converted to P.O.
whenever this P.O is updated with confirmation category like acknowledgement or inbound delivery it should update Sales order schedule line for the delivery date. but this is not happening, what is the configuration required for this.
Kindly reply.
Regards,
Venkatesh
When you run availability check on the sales order it should confirm the new date. The delivery date is not changed automatically.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Can you be little more clear on your requirement.
Secondly, is it that for all individual requirements a PR is mandatory. I dont think so. As in consignment sale and returnable packaging or Make to order there is no PR raised. Open for discussions.
Regards,
Sam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
when stock is not available then the customer order is booked as special requirement and P.R created against that order. Then the P.R is converted in to P.O and P.O is updated by O.A or Inbound delivery but the delivery dates from O.A or inbound does not update the sales order schedule line.
Regards,
Venkatesh
User | Count |
---|---|
88 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.