Hi all,

The system allows to create a Pre-dated sales order. What is the effect of ATP quantities in such a situation? Kindly advice...

Thanks and Regards,

Deepak Prasanna S

Accepted Solutions (1)

Accepted Solutions (1)

former_member183879
Active Contributor
0 Kudos

Still ATP is based on Requested Delivery date and other lead times and that is independent of what date you are giving as Document date or Creation date.

So ATP dates are not affected because of this, as ATP dates are based on Requested Delivery date and not based on Document date or Creation date.

However if you change your RDD, then ATP will also be a point of impact.

Hope this clarifies your doubt.

Reward if this helps.

Answers (1)

Answers (1)

Manoj_Mahajan78
Active Contributor
0 Kudos

Hi..

ATP uses Requested delivery date for calculations..

Regds