on 10-22-2007 10:55 AM
Hi all,
Besides having config in SPRO, those steps i can follow step by step in the Product Cost Planning and Cost Object Controlling, what else i need to set up for the whole COPC config?
For Moving Average Price we just put V in the MM01 and for Standard Price we put S in MM01.
For Standard Price, we need to set up standard cost estimate.
What else do we need?
Best regards,
Lucas
Hi,
ME11 may be required.
Find this useful link
http://www.sap-topjobs.com/SpecialPP/samplepc.doc
Regards,
Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Can you give me more detail config document?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Find some more links
http://help.sap.com/bp_bblibrary/600/h++tml/M08_EN_DE.htm
Product costing:
Regards,
Murali