can any body send me the Business Blue Print for a complete subcontracting industry i.e no in-house production takes place.
please send to nani_uvrs@yahoo.co.in
thanks in advance
ravi
hi gurus
Please send any sample blue print of PP for a discrete manufacturing industry to my id ravi.ballamudi@gmail.com.
thanks in advance
ravi kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello ravi,
Can you please explain the proess. Without this it is difficult to explain.
Rajnish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi rajinish
Actually my client is a construction equipment manufacturing company and there is no inhouse production i.e once they got the order they will give subcontract to vendors and finally they will assemble the product at the customers site after receiving the all components from subcontractors.
thanks
Ravi
Hi,
Since no In-house production takes place, the Planned Order can be converted to Subcontracting Purchase Order and after receiveing from the vendor GR is completed.After quality check, the materila moves to stock. With the final product assembled at the site, production order is raised and the dependent materials are picked from the stores.
Hope this helps... Any further scenarios or corrections are expected..
- Thaila Shree
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.