Dear friends,
I have Sol Man 4.0 with SP 12. In My Sol Man system, i have added cproject suite (software component CPRXRPM, Release 400, level 0007).
I have created project , phase & task in cproject suite.
While i am doing staffing, for my phase, i am getting following runtime error.
-
Business Server Page (BSP) error
What happened?
Calling the BSP page was terminated due to an error.
SAP Note
The following error text was processed in the system:
BSP Exception: Internal Error in Business Server Page Runtime.
Program CL_BSP_PAGE_BASE==============CP
Include CL_BSP_PAGE_BASE==============CM01A
Line 115
Error type:
Your SAP Business Server Pages Team
-
Please help me on this..will be very much appreciated
Regards
Senthil
hi senthil ,
Have you create the business partner in c project backend system use T code : BP
thanks
sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sunil,
The same way i have done. But still i am getting this BSP application error.
Just check in IMG....
Collaboration projects-->Resource Mgmt>Define Project Roles>Select the project role type & go to "Details" view. There you can find one field called "Staffed by"--In this field i am mentioning as "Project Lead". Where in IMG, we are defining the functions for "Project Lead"?
Is "Project Lead" can staff the resource?
Reagdrs
Senthil
hi senthil ,
1) first you create the BP ( then goto change BP and select BP as employ and save it ) all in c project backend.
2) come to c project > Resoures> staffing
then there is option Resoures enter your BP no there or go for search .
once you give the number then select the button staff.
3) save
4) than you can aasing this resoure to asing the phase
thanks
sunil
Dear Sunil,
Byt my problem is, If i click on "Staffing" tab, i am immeadiately getting the BSP error only.
I have referred the config guide in help.sap.com...There it has been mentioned that
"
You have set the Extended Staffing Process flag for the role assigned to the project
in the IMG by choosing the path: SAP IMG ® cProjects ® Resource Management ® Define Project Roles for Project Role Type in order access the Staffing Process tab."---Thjis guide for cproject 3.1.But i am working with cproject 4.0.
Can u able guide me, in cproject 4.0, where i have activate the above flag?
Regards
Senthil